Can I set GoAnywhere to run just one concurrent job?

View some of the Frequently Asked Questions to our support staff. Included are some tips and tricks making this forum ideal for users getting started with GoAnywhere Director. Note: Users can reply to existing topics but only our support staff can add new topics to this forum.
1 post Page 1 of 1

Support_Duane

Support Specialist
Posts: 66
Joined: Thu Mar 05, 2009 3:49 pm

Post by Support_Duane » Tue Mar 10, 2009 10:27 am
To set GoAnywhere to run only one submitted project at a time, do the following:
  • Move the cursor over the Administration menu.
  • Select the Global Setting menu option.
  • Under Global Settings click on the Runtime tab
  • Change the Maximum pool size to 1.
  • Click the save button.
  • Restart GoAnywhere.


Note: This will only limit projects that are submitted in batch mode. It is still possible to run multiple projects concurrently by executing them interactively. i.e. If the [Execute Project] button of a project is clicked while another project is running in batch, it would be possible to have both projects running.

For information on how to stop & start GoAnywhere view the following topic:
https://forum.goanywhere.com/viewtop ... &t=35&p=35