project schedule for last weekday of the month

Post any question you may have in regards to GoAnywhere Director and let our talented support staff and other users assist you.
2 posts Page 1 of 1

castewa

Posts: 2
Joined: Wed Nov 16, 2011 12:34 pm

Post by castewa » Wed Nov 16, 2011 12:58 pm
Is it possible to create a schedule that will run a job on the last *weekday* of the month?

Support_Julie

User avatar
Support Specialist
Posts: 91
Joined: Thu Mar 05, 2009 3:49 pm
Location: Ashland, NE USA

Post by Support_Julie » Wed Nov 16, 2011 4:48 pm
With the current version (3.6.1) this cannot be achieved.

However, with the use of holiday calendars (available in the next release), you will be able to attain that behavior.
Julie Rosenbaum
Sr Support Analyst
e. [email protected]
p. 1.800.949.4696
w. HelpSystems.com
2 posts Page 1 of 1